patching...
Welcome back, Patch Blogger!

Wssc

Friday, May 10, 2013

WSSC 'Holes Through' in New Water Main Project

Washington Suburban Sanitary Commission engineers recently completed the tunnel-boring process to build the Bi-County Water Tunnel Project.

Washington Suburban Sanitary Commission engineers recently completed the last leg of the 5.3-mile tunnel-boring process necessary to build the Bi-County Water Tunnel Project, according to a WSSC news statement. "Hitting a target 4.5 miles away when boring a tunnel 200 feet underground is quite a feat. On Friday, April 26, the tunnel-boring machine "hit the target just a few feet off dead center, breaking through the wall of a shaft near Tuckerman Lane and I-270," the statement reported. Miners call that target-hitting moment "holing through," WSSC said. As soon as the tunnel-boring machine is removed from the tunnel shaft, pipe installation will begin. The tunnel runs about 200 feet underground along Interstate 270 and Interstate 495, and …

dcr20854

10:18 am on Saturday, May 11, 2013

Thanks for reporting this! I had wondered what was going on at that site, and now I know! Potomac Patch is an invaluable source of quality local reporting.   more ›

Monday, April 15, 2013

WSSC Proposes 7.25 Percent Rate Increase

Montgomery County Council's Transportation, Infrastructure, Energy and Environment Committee reviews the request on Monday morning.

The Washington Suburban Sanitary Commission is proposing a 7.25 percent rate increase for water and sewer use in Montgomery County, according to a news release from the county council's office. On Monday, April 15, at 9:30 a.m., the Montgomery County Council's Transportation, Infrastructure, Energy and Environment Committee, chaired by Council Member Roger Berliner, will review WSSC's operating budget request. Council Members Nancy Floreen and Hans Riemer also are on the committee. The budget request comes as investigations are made into the cause of a massive water main break on Connecticut Avenue in Chevy Chase on March 18. Washington Suburban Sanitary Commission engineers still do not know what caused the break, but they say that the …

Monday, April 8, 2013

Report: Cause of Connecticut Ave. Water Main Break Still Unknown

The fiber optic monitoring system meant to warn WSSC of impending breaks in the water main did not fail, WSSC engineers said, Bethesda Now reported.

Washington Suburban Sanitary Commission engineers still do not know what caused the massive water main break on March 18 at the intersection of Connecticut Avenue and Chevy Chase Lake Drive, but they say that the fiber optic monitoring system installed in the pipes in 2010 did not fail, Bethesda Now reported. The monitoring system detects only the sounds of snapping steel wires in the concrete pipes, but as the steel wires did not snap before the break, the monitoring system could not detect the impending break, WSSC chief engineer Gary Gumm told the Montgomery County Council’s Transportation and Environment Committee on Monday morning, Bethesda Now reported. But, "[that] is a distinction however that has very little comfort to our …

Friday, April 5, 2013

Connecticut Ave. Water Main Break Investigations Continue

On Monday, at 9:30 a.m., the Montgomery County Council's Transportation, Infrastructure, Energy and Environment Committee will be briefed on what has been learned so far about the water main break at Chevy Chase Lake Drive and Connecticut Avenue.

As cleanup continues around the crater formed by March 18's massive water main break at Connecticut Avenue and Chevy Chase Lake Drive, many questions have arisen about how the water main break—from which 60 million gallons of water were lost, necessitating mandatory water restrictions in two counties—could have happened. This Monday, at 9:30 a.m., the Montgomery County Council's Transportation, Infrastructure, Energy and Environment Committee will be briefed on what has been learned so far about the break, according to an email statement from Neil Greenberger, spokesman for the Montgomery County Council. The Washington Post reported that a Chevy Chase resident noticed "water squirting up from an opening in a circular metal plate embedded …

Saturday, March 23, 2013

WSSC Lifts Water Restrictions Necessitated by Water Main Break in Chevy Chase

Water restrictions necessitated by a massive water main break in Chevy Chase on Monday, March 18, were lifted at about 6 p.m. Saturday.

Mandatory water restrictions necessitated by a massive water main break in Chevy Chase Monday were lifted at around 6 p.m. on Saturday, according to a Montgomery County email alert. The Washington Suburban Sanitary Commission lifted the water restrictions—which asked residents of Montgomery and Prince George's counties to reduce water consumption by 10 percent—following the completion of repair work to the broken 60-inch-in-diameter main. The restrictions were in place for four and a half days. The ruptured main is back in service, "but restoration of the area, including roadway, sidewalk, removal of damaged trees and work on the stream bed near the break, will take weeks," the alert reported. The additional work will require the right-…

Friday, March 22, 2013

Repairs to Massive Water Main Break Nearly Done

WSSC hopes to have the repaired line back in service by the end of the weekend.

Repairs to the 60-inch-in-diameter water main that burst Monday night on Connecticut Avenue in Chevy Chase are nearly complete. A new pipe section was put in place Thursday, and the grout in the pipe joints cured overnight. Early Friday morning, Washington Suburban Sanitary Commission crews "slowly opened a valve to begin filling the isolated stretch of pipe," according to a statement on the WSSC website. On Friday, WSSC crews were slated to "[flush] the repaired line during the day, which is part of the standard decontamination process to ensure water quality, before putting the transmission main back into service," the statement read. The Acoustic Fiber Optic monitoring system was re-installed yesterday, The Washington Post reported. …

Tuesday, March 19, 2013

Update: Montgomery, Prince George's Counties Ordered to Restrict Water Usage

WSSC crews determined that the pipe that broke was a 60-inch water transmission pipe connected to a 54-inch line—not a 54-inch pipe, as originally reported.

Update, 1 p.m., Thursday, March 21: Repairs to the 60-inch water main that burst Monday night in Chevy Chase continued on Thursday. Washington Suburban Sanitary Commission crews removed the damaged 20-foot section of the pipe and are working to weld a new section in place, according to a WSSC statement issued at noon Thursday. "Once repairs to the pipe are complete later this afternoon it will take several more days for the work to conclude," the statement read. Only the right-hand northbound lane of Connecticut Avenue between Dunlop Street and Manor Road in Chevy Chase Lake remained closed Thursday. Mandatory water restrictions continued Thursday for Montgomery and Prince George's counties. "There is evidence that [water] consumption is …

Comment_arrow

Ian Cooper

9:20 am on Friday, March 22, 2013

I wish they would tax us so that they can maintain infrastructure properly (a 3 story high waterspout is evidence that they are not doing what's necessary), but they won't. Presumably I'm being held hostage by those who want something for nothing. As for eliminating one toilet flush per day, a 10% reduction in water usage is a bit more than that. As for me, I've done no laundry since the pipe …   more ›

Thursday, January 10, 2013

WSSC to Hold Meeting on Rockville Stream Work

The utility will outline its Sewer Repair, Replacement and Rehabilitation program.

  Streams in Rockville will be undergoing a bit of surgery in coming months courtesy of the Washington Suburban Sanitary Commission. Want to learn about what WSSC crews will be doing as they work on sewer pipes and manholes in Rockville’s stream beds and river sheds? WSSC representatives will outline the utility’s Sewer Repair, Replacement and Rehabilitation (also known as SR3) program at a meeting from 7:30 to 9 tonight at Ritchie Park Elementary School, at 1514 Dunster Road in Rockville. The Cabin John stream bed will be the first area of Rockville to see work, according to a message on the City of Rockville’s website. The Cabin John sewer basin stretches south of Montrose Road along Interstate 270 and the Capital Beltway to the Potomac …

Tuesday, December 4, 2012

Report: NIH Delinquent for $491K on Water Bill

The National Institutes of Health owes the Washington Suburban Sanitary Commission nearly $1 million, The Gazette reports.

Bethesda's National Institutes of Health owes the Washington Suburban Sanitary Commission nearly $1 million and is delinquent by nearly $491,000 on the bill, The Gazette reports. The outstanding debt made up much of the $670,000 that was owed WSSC by federal agencies in November, according to the report. An NIH spokesman told The Gazette that a June and August bill were processed late. The first was paid, the spokesman said, and the second should be remitted to WSSC shortly, which should bring the account balance to zero. Read the full story at The Gazette.

Sandra James

5:46 pm on Wednesday, December 5, 2012

Wow, as an employee of NIH, I am totally embarrassed.   more ›

Monday, October 8, 2012

Water Rate Increase, Council Salaries, Rapid Bus Network on Montgomery County Council, Planning Agenda

Planning Board schedule, zoning amendment and study into top county salaries top Oct. 9 agenda.

The Montgomery County Council gets back to work Tuesday after a two-week break, taking on an amendment to the Commercial/Residential Zone, a study of salaries for councilmembers, the county executive, sheriff and state's attorney, and its twice-annual meeting on the County Planning Board's work schedule. DECISION ITEMS  INTRODUCTIONS HEARINGS The council will also have its twice-annual meetings with the Montgomery Business Development Corporation and the County Planning Board. The Planning Board meeting will update the council on the study for a countywide rapid-bus network and on the revision of the county's zoning ordinance, which is on track to present to the council for approval in December. The Planning Board will also hash over its …

Bob Hydorn

9:25 am on Tuesday, October 9, 2012

PART 2 OF LETTER TO COUNTY COUNCIL Our community worked very hard to prepare its Vision 2030 report in time so that it would nicely coordinate with the original master plan start date of May2012. Then, that date was delayed until mid-2013. It is with great disappointment that we learn of the potential of another delay to update the Gaithersburg East/Montgomery Village Master Plan, which could be …   more ›

Got a Hot Tip?
 
 

Videos